We have made a lot of progress at our Lobos Views home since the beginning of August! Interior framing on the first and second level is complete and is almost complete on the third level.

SONY DSC


Above is a photograph of the front of the home. The X-bracing for additional lateral support of the structure has been installed throughout the home as well. You can see where the X-bracing installed on the south wall of the living room in the photo above.

SONY DSC


The main living area of the home is starting to take shape as well. Above, moving counter-clockwise from the bottom left of the photo you can see the living room, dining room, kitchen and two bedrooms on the third level of the home.

SONY DSC


Above is another image of the progress on the third floor bedrooms taken from the future patio area off the living room/dining room.

SONY DSC


On the fourth level of the home, the board form for the concrete roof eave is being installed in the master suite area.

SONY DSC


Above is another view from the fourth level of the home looking towards the pool.